EXPERTISE
YOU CAN
COUNT ON

Dewatering and Treatment Case Studies

High Flow Dewatering and Excavation

Dewatering and Treatment


High Flow Dewatering and Excavation        top

A regional petroleum distributor contracted with Aztech Technologies, Inc. to oversee a facility reconstruction at one of their gasoline stations and convenient stores in Westchester County, New York. The site is located in a deltaic sand deposit near a major surface body of water, and the local groundwater table is tidally influenced. To facilitate in the reconstruction activities, soil excavation and soil dewatering were implemented at the site. In order to achieve the goals set forth by the client, Aztech worked with the general contractor to develop a concise schedule, engineer and build a portable treatment system to handle the influx and sustained groundwater flow at the site, oversee the soil excavation and implement insitu chemical oxidation to stimulate the natural biodegradation of residual petroleum impacts.

250 gpm Portable Air Stripper
view full size

During the preliminary stages of the project, Aztech advanced two geotechnical soil borings to provide information to the general contractor, so that a proper shoring and soil dewatering system would be emplaced. Aztech used their own truck mounted hollow stem auger-drilling rig, equipped with soil sampling equipment to drilling the geotechnical soil borings. An Aztech geologist oversaw the drilling operations and logged the soil cores. Additional soil borings were also advanced to define the extent of the petroleum impacts onsite. In total seventeen soil borings were advanced to define the source material soil excavation limits.

Aztech obtained a Stipulation Agreement with the New York State Department of Environmental Conservation for the treatment and discharge of petroleum impacted groundwater at the site on behalf of the client. Additionally, Aztech obtained an air discharge permit with the Westchester County Department of Health for point emissions air discharge.

Soil Dewatering & Excavation
view full size

For the dewatering treatment system, Aztech used the groundwater quality data provided from routine quarterly monitoring and sampling events and pump-down test data to engineer and build a trailer mounted portable treatment system. The system was designed to effectively treat up to 250-gallons per minute using four sediment filters, two air-strippers, and computerized controls. The treatment system was constructed in 17 days and mobilized to the site for operations. Aztech provided technicians to operate and maintain the treatment system throughout the reconstruction activities. Approximately 1.8 million gallons of groundwater were treated over an eight-week period, with 1.2 million gallons during the first eight days as the site water table was dropped.

For the soil excavation, handling, and disposal phase of the project, Aztech coordinated with the general contractor the construction contractor, the client, and the disposal facilities to progress the project and maintain the milestones and deadlines established by the client. In total, approximately 3,600 tons of petroleum impacted soil was excavated and treated by thermal desorption during an eight-week period.

Following the reconstruction activities, Aztech installed seven groundwater monitoring wells throughout the site. These monitoring wells are currently being used to determine the effectiveness of the source material excavation in remediating the site groundwater. Aztech has also performed one insitu chemical oxidation injection event to further reduce localized groundwater impacts. Preliminary groundwater data indicates that the source material excavation and insitu chemical oxidation application have successfully provided remediation at the site. It is Aztech's goal to achieve regulatory closure at the site within the calendar year.


Dewatering and Treatment        top


Aztech Technologies, Inc. was retained to excavate petroleum-impacted soil present beneath the the future site of a public building being constructed in Schoharie County, NY.
16' Portable Air Stripper
view full size
The building site was a vacant parcel of land that had once been occupied by a gasoline retail facility and service garage. Petroleum-impacted soil and groundwater were encountered during a geotechnical investigation at the property.

Groundwater was encountered at approximately 10 feet below grade. However at 12 to 13 feet below grade, the geology coarsened from overlying sands and silts to well-rounded gravel and cobbles. The latter produced a significant amount of groundwater. As such, groundwater was frequently retrieved from the
excavation with a vacuum truck. Additionally, groundwater was removed via trash pumps set into the excavation. The water was subsequently treated by Aztech’s portable dewatering treatment equipment. A total of 87,372 gallons of groundwater was treated through this system and discharged.
Portable Air Stripper
view full size

As the excavation was dewatered, petroleum impacted material was excavated from between 6 and 14 feet below grade. However, in some areas it was encountered at shallower depths (e.g. three to four feet below grade). A total of 6,200 tons of petroleum-impacted soil was removed for disposal.

Aztech’s observations indicated that apparently heavily impacted soil did not have the expected negative influence on groundwater quality. Since the vast majority of source material was removed natural attenuation was sufficient to complete site remediation.